Bexs will join Mission Council June X to do a live demo of our Circle setup. This was rescheduled due to the Mission Council May meeting needing full time for the consultant.
Between 50–70% of parishes will be onboarded by Convention, with about 60% expected on the current schedule.
QUICK LINKS:
⚠️ NOTICE: Schedule Update -Timeline Adjustment Due to Data & Access Delays
As part of our ongoing implementation work, we’ve encountered delays related to data exports and full-access availability of the data that is in realm Realm. These dependencies are critical to ensuring a complete and accurate migration into Circle. Because of this, the project timeline has experienced an approximately 3-week delay.
What This Means
The overall schedule has been rebaselined to reflect this shift. The schedule is updated on this page.
All downstream phases have been adjusted accordingly to maintain quality and continuity.
No changes to main timeframes (convention). Bexs will work to mitigate timeslip in other ways.
Why This Matters
Rather than proceeding with incomplete or inconsistent data, we are prioritizing:
Data integrity (clean, usable, trustworthy records).
System reliability at launch.
Reduced rework post-import of data.
Current Status
Partial data export from Realm received. Mike is made aware and is receiving Bexs remaining data through manual run reports.
Updated milestones are now reflected across the implementation dashboard.
The team remains aligned on delivery with the revised schedule.
Progress Bar
Implementation Overview
Design
Platform learning, structure planning, and UX design for the Diocese.
Build
Core spaces, navigation, permissions, and staff setup.
Pilot
MAT convenors and a small group of pilot parishes test the platform.
Resource Population
Ministry areas populated (Creation Care, COM, Altar Guild, Wardens, etc.).
Parish Rollout
Parishes onboarded weekly in batches of 5–7 beginning August.
Convention
Diocese-wide visibility and storytelling about Circle adoption.
Final Implementation
All parishes expected to be onboarded by mid-November.
Stabilization & Buffer
Support, documentation improvements, and system stabilization through the end of the year.
Circle Implementation – Leadership Benchmarks
| Milestone | Target Date | Notes |
|---|---|---|
| Circle Platform Approval | Feb 10, 2026 | Approval received to begin implementation planning and development. |
| Implementation Work Begins | Feb 24, 2026 | Active implementation begins after runway clearing and staff retreat week. |
| Realm System Closure | Apr 21, 2026 | Adjusted (+3 weeks). Realm use discontinued so Circle becomes the primary collaboration platform. |
| Staff Active in Circle | Apr 27, 2026 | Adjusted (+3 weeks). Internal staff begin testing the platform and workflows. |
| Staff Feedback & Refinement | Early May 2026 | Adjusted (+3 weeks). Internal feedback gathered to improve usability before expanding to ministry leaders. |
| MAT Convenors & RM Active | May 12, 2026 | Adjusted (+3 weeks). Mission Action Team and RM leaders begin onboarding and testing collaboration spaces. |
| Clergy Conference | Late April 2026 | Occurs during transition window; awareness and informal demos still possible. |
| First Pilot Parish | May 26, 2026 | Adjusted (+3 weeks). Pilot parish onboarding begins. |
| Pilot Feedback Complete | Jun 7, 2026 | Adjusted (+3 weeks). Structured feedback collected from pilot parishes. |
| All Parish Shells Built | Jul 6, 2026 | Adjusted (+3 weeks). Standard parish spaces created behind the scenes. |
| Ministry Resource Population | Jul 7 – Aug 3, 2026 | Adjusted (+3 weeks). Core ministry spaces populated (Creation Care, COM, Altar Guild, Wardens, etc.). |
| Marketing Materials Completed | Aug 5, 2026 | Adjusted (+3 weeks). Marketing materials and trainings finalized. |
| Public Launch | Aug 24, 2026 | Adjusted (+3 weeks). Circle publicly introduced as the shared diocesan digital community. |
| Parish Onboarding Begins – Batch A | Sep 2, 2026 | Adjusted (+3 weeks). First 5–7 parishes begin onboarding. |
| Parish Onboarding – Batch B | Sep 9, 2026 | Adjusted (+3 weeks). Second group of 5–7 parishes onboard. |
| Parish Onboarding – Batch C | Sep 16, 2026 | Adjusted (+3 weeks). Third group of 5–7 parishes onboard. |
| Parish Onboarding Continues | Sep – Dec 2026 | Adjusted (+3 weeks). Additional batches onboard weekly until all 90 parishes are supported. |
| Annual Convention | Oct 2–3, 2026 | Timing unchanged. Opportunity to highlight Circle and early adoption (~50–60% onboarded). |
| Parish Onboarding Complete | Dec 8, 2026 | Adjusted (+3 weeks). All parishes expected to have access and onboarding support. |
| Stabilization and Support / Buffer | Dec 9, 2026 – Jan 15, 2027 | Adjusted (+3 weeks). Support, documentation, and improvements. Buffer aligns carefully with Advent/Christmas realities. |
Changelog: April 22, 2026 - 3 week slippage due to Realm data delays. Discussed and mitigation planned with MF.