CIRCLE IMPLEMENTATION
DASHBOARD

  • Bexs will join Mission Council June X to do a live demo of our Circle setup. This was rescheduled due to the Mission Council May meeting needing full time for the consultant.

  • Between 50–70% of parishes will be onboarded by Convention, with about 60% expected on the current schedule.

QUICK LINKS:

⚠️ NOTICE: Schedule Update -Timeline Adjustment Due to Data & Access Delays

As part of our ongoing implementation work, we’ve encountered delays related to data exports and full-access availability of the data that is in realm Realm. These dependencies are critical to ensuring a complete and accurate migration into Circle. Because of this, the project timeline has experienced an approximately 3-week delay.

What This Means

  • The overall schedule has been rebaselined to reflect this shift. The schedule is updated on this page.

  • All downstream phases have been adjusted accordingly to maintain quality and continuity.

  • No changes to main timeframes (convention). Bexs will work to mitigate timeslip in other ways.

Why This Matters

Rather than proceeding with incomplete or inconsistent data, we are prioritizing:

  • Data integrity (clean, usable, trustworthy records).

  • System reliability at launch.

  • Reduced rework post-import of data.

Current Status

  • Partial data export from Realm received. Mike is made aware and is receiving Bexs remaining data through manual run reports.

  • Updated milestones are now reflected across the implementation dashboard.

  • The team remains aligned on delivery with the revised schedule.

Progress Bar

Circle Implementation Progress Week 1 of 32
0%
Project Start: Feb 24, 2026 Projected Launch: Oct 4, 2026

Implementation Overview

Design

Platform learning, structure planning, and UX design for the Diocese.

Build

Core spaces, navigation, permissions, and staff setup.

Pilot

MAT convenors and a small group of pilot parishes test the platform.

Resource Population

Ministry areas populated (Creation Care, COM, Altar Guild, Wardens, etc.).

Parish Rollout

Parishes onboarded weekly in batches of 5–7 beginning August.

Convention

Diocese-wide visibility and storytelling about Circle adoption.

Final Implementation

All parishes expected to be onboarded by mid-November.

Stabilization & Buffer

Support, documentation improvements, and system stabilization through the end of the year.

Circle Implementation – Leadership Benchmarks

Milestone Target Date Notes
Circle Platform Approval Feb 10, 2026 Approval received to begin implementation planning and development.
Implementation Work Begins Feb 24, 2026 Active implementation begins after runway clearing and staff retreat week.
Realm System Closure Apr 21, 2026 Adjusted (+3 weeks). Realm use discontinued so Circle becomes the primary collaboration platform.
Staff Active in Circle Apr 27, 2026 Adjusted (+3 weeks). Internal staff begin testing the platform and workflows.
Staff Feedback & Refinement Early May 2026 Adjusted (+3 weeks). Internal feedback gathered to improve usability before expanding to ministry leaders.
MAT Convenors & RM Active May 12, 2026 Adjusted (+3 weeks). Mission Action Team and RM leaders begin onboarding and testing collaboration spaces.
Clergy Conference Late April 2026 Occurs during transition window; awareness and informal demos still possible.
First Pilot Parish May 26, 2026 Adjusted (+3 weeks). Pilot parish onboarding begins.
Pilot Feedback Complete Jun 7, 2026 Adjusted (+3 weeks). Structured feedback collected from pilot parishes.
All Parish Shells Built Jul 6, 2026 Adjusted (+3 weeks). Standard parish spaces created behind the scenes.
Ministry Resource Population Jul 7 – Aug 3, 2026 Adjusted (+3 weeks). Core ministry spaces populated (Creation Care, COM, Altar Guild, Wardens, etc.).
Marketing Materials Completed Aug 5, 2026 Adjusted (+3 weeks). Marketing materials and trainings finalized.
Public Launch Aug 24, 2026 Adjusted (+3 weeks). Circle publicly introduced as the shared diocesan digital community.
Parish Onboarding Begins – Batch A Sep 2, 2026 Adjusted (+3 weeks). First 5–7 parishes begin onboarding.
Parish Onboarding – Batch B Sep 9, 2026 Adjusted (+3 weeks). Second group of 5–7 parishes onboard.
Parish Onboarding – Batch C Sep 16, 2026 Adjusted (+3 weeks). Third group of 5–7 parishes onboard.
Parish Onboarding Continues Sep – Dec 2026 Adjusted (+3 weeks). Additional batches onboard weekly until all 90 parishes are supported.
Annual Convention Oct 2–3, 2026 Timing unchanged. Opportunity to highlight Circle and early adoption (~50–60% onboarded).
Parish Onboarding Complete Dec 8, 2026 Adjusted (+3 weeks). All parishes expected to have access and onboarding support.
Stabilization and Support / Buffer Dec 9, 2026 – Jan 15, 2027 Adjusted (+3 weeks). Support, documentation, and improvements. Buffer aligns carefully with Advent/Christmas realities.

Changelog: April 22, 2026 - 3 week slippage due to Realm data delays. Discussed and mitigation planned with MF.